Moosburg-Bruckberg
The Catenary Systems Germany division or EUROPTEN Deutschland GmbH has been commissioned to renew the overhead contact line system on the Moosburg - Bruckberg section of the line. As part of this project, we have been awarded a contract for the renewal of the overhead contact line system in the regional section of Deutsche Bahn AG (DB).
This project involves the operational testing of the innovative EUROPTEN concrete pile and EUROPTEN steel mast system.
Project Area
Fahrleitung Deutschland
Project Start
11.2024
Project End
12.2025
Client
DB InfraGO AG
Indicators
Implementation planning and revision planning
3 in-situ concrete foundations
234 driven pile foundations
206 steel masts
Laying 16,978 m KW
incl. dismantling
Clearing 5,590 m² construction site