Project

Moosburg-Bruckberg

The Catenary Systems Germany division or EUROPTEN Deutschland GmbH has been commissioned to renew the overhead contact line system on the Moosburg - Bruckberg section of the line. As part of this project, we have been awarded a contract for the renewal of the overhead contact line system in the regional section of Deutsche Bahn AG (DB).

This project involves the operational testing of the innovative EUROPTEN concrete pile and EUROPTEN steel mast system.

Project Area

Fahrleitung Deutschland


Project Start

11.2024


Project End

12.2025


Client

DB InfraGO AG


Indicators

Implementation planning and revision planning
3 in-situ concrete foundations
234 driven pile foundations
206 steel masts
Laying 16,978 m KW
incl. dismantling
Clearing 5,590 m² construction site

Hermann Wogowitsch

Techn. Managing Director