Project

GKB Overhead line pile foundation and overhead line pile erection work

At the end of 2021, Europten was awarded the contract for the pile driving and mast erection work in the form of a framework agreement with a term from 2022 to 2026. The construction project is divided into 5 construction phases, with a total of around 2,600 mast locations to be erected. The foundations will be constructed by Europten largely using pile driving techniques, with reinforced concrete masts being erected in accordance with ÖBB standards. The main construction phases are to take place annually in the summer months, for which permanent closures are planned.

Project Area

Fahrleitung AT/CH/SI


Project Start

01.2022


Project End

12.2026


Client

Graz -Köflacher Bahn und Busbetrieb GmbH


Indicators

2,600 Mast locations