GKB Overhead line pile foundation and overhead line pile erection work
At the end of 2021, Europten was awarded the contract for the pile driving and mast erection work in the form of a framework agreement with a term from 2022 to 2026. The construction project is divided into 5 construction phases, with a total of around 2,600 mast locations to be erected. The foundations will be constructed by Europten largely using pile driving techniques, with reinforced concrete masts being erected in accordance with ÖBB standards. The main construction phases are to take place annually in the summer months, for which permanent closures are planned.
Project Area
Fahrleitung AT/CH/SI
Project Start
01.2022
Project End
12.2026
Client
Graz -Köflacher Bahn und Busbetrieb GmbH
Indicators
2,600 Mast locations