Graz-Autal train station

As part of the electrification of the Styrian Eastern Railway, EUROPTEN was awarded the contract to install the overhead lines on the section from Autal to Graz Don Bosco, as well as to construct Track Group 300 at Graz Central Station, in the summer of 2025.

The project will be carried out in a total of four construction phases while rail service continues. The work covers Track Group 300 at Graz Central Station, the route sections Graz Don Bosco–Graz Ostbahnhof, Graz Ostbahnhof–Messendorf, and Messendorf–Autal, as well as the stations Don Bosco, Graz Ostbahnhof, Messendorf, and Autal. Due to operational constraints, the work will largely be carried out during night shifts. The main work by EUROPTEN began in February 2026 and is expected to be completed by mid-December 2026.

Project Area

Fahrleitung AT


Project Start

07.2025


Project End

12.2026


Client

ÖBB Infrastruktur AG


Indicators

500 boom units
10 km of Type 1.1 track
5 km of Type 1.2 track