Project

380-kV-Ltg. Wesel – Pkt. Meppen, BL 4201_7

As part of the construction of the new approx. 57.9 km long 110/380 kV extra-high voltage overhead line Wesel - Pkt. Meppen, Bl. 4201 in the section from Pkt. Haddorfer See to Pkt. Meppen, we are building section 4, from pylon 307/4201 to pylon 344/4201 incl. cable laying on a line length of approx. 16.5 km as well as the connection to the already installed TenneT overhead line. Construction began in October 2024 and the foundation and pylon installation work for the 39 new pylons is currently underway. Construction is scheduled to end in September 2026.

Project Area

Freileitung DE


Project Start

10.2024


Project End

09.2026


Client

Amprion


Indicators

29.9 million € project volume
39 pylons with 2,853 tons of pylon steel
16.5 km of pipeline length
Approx. 22,000 m² of road construction area
184 large bored piles

Paul Knabel

project manager