380-kV-Ltg. Wesel – Pkt. Meppen, BL 4201_7
As part of the construction of the new approx. 57.9 km long 110/380 kV extra-high voltage overhead line Wesel - Pkt. Meppen, Bl. 4201 in the section from Pkt. Haddorfer See to Pkt. Meppen, we are building section 4, from pylon 307/4201 to pylon 344/4201 incl. cable laying on a line length of approx. 16.5 km as well as the connection to the already installed TenneT overhead line. Construction began in October 2024 and the foundation and pylon installation work for the 39 new pylons is currently underway. Construction is scheduled to end in September 2026.
Project Area
Freileitung DE
Project Start
10.2024
Project End
09.2026
Client
Amprion
Indicators
29.9 million € project volume
39 pylons with 2,853 tons of pylon steel
16.5 km of pipeline length
Approx. 22,000 m² of road construction area
184 large bored piles