Project

380-kV-Ltg. from Dörpen to West-Niederrhein – Los 2b

Our extensive project for the 380 kV line from Dörpen to West-Niederrhein also includes the LOS 2b project. This consists of a total of 8 impressive 380 kV pylons. Our current focus is on building the foundations for these pylons. This work requires a great deal of precision and detailed work. At the same time, the pre-assembly of the pylons is underway. Materials are being ordered in preparation for the cable pulling work. The cable pulling work is planned for mid-2025. The end of construction is planned for the end of 2025.

Project Area

Freileitung DE


Project Start

02.2025


Project End

12.2025


Client

TenneT


Indicators

4.9 million € project volume
Construction of 8 new masts
8 slab foundations with a total of 1,860 m³ of concrete
600 tons of mast steel
3.5 km of cable pull
A total of 28,100 m² of road construction

Gerrit Eilers

project manager