380 kV Pulgar - Vieselbach line; West section (Bad Sulza - Vieselbach)
According to the planning, the dismantling work of the 380 kV existing line will be carried out after and during the construction of the 380 kV new replacement line.
Lot 6 - section from pylon 206 to pylon 248 / Vieselbach substation
Partial dismantling of the existing 380 kV Pulgar-Vieselbach line:
- Line dismantling from existing pylon 201 to pylon 241 (41 pieces)
- Existing pylons to be retained (old pylon no. 241 - new pylon no. 243)
- Complete dismantling (pylon, foundation and stranding)
The commissioning of line 589, including the upgraded switchgear panels in Pulgar and Vieselbach, was successful. The line was approved for continuous operation in July 2025.
The remaining work on line 590 is scheduled to be completed by September 2025. The existing line will then be completely dismantled by the end of the year.
Project Area
Overhead Power Lines Germany
Project Start
09.2023
Project End
12.2025
Client
50Hertz Transmission
Indicators
- New pylon construction from pylon 206 to pylon 247 (pylon 248 existing pylon formerly pylon no. 241)
- Cable pull from pylon 205 to pylon 248 / UW Vieselbach
Route length of approx. 16.6 km
- Foundation work and mast erection from mast 205 to mast 247 (42 pieces)
- Installation of HighStep system from pylon 206 to pylon 247 (42 pieces)